There should be an option to enter the "Total S/C Invoices to Date" when starting a S/C payment.
This value is regularly used on subcontractor payment schedules and is reflected by their Gross Claim to Date. The current Jobpac method requires a manual calculation for the majority of payments
Company | Argon Constructors |
Job Title / Role | Senior QS |
I need it... | 1 month |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
thanks Michael. Understood.
Our current process works well, its just the claim entry method using a "This Claim" value that seems disjointed.
Would be great to see an option for entering subbie claims with the Total to Date.
Got it. And would you be interested in configuring the system to force the
linking of the registered subbi invoices to the claims you are authorising,
which would automate the calculation of Subbie claim values? Just a
thought. If that sounds of interest we could assist you with that
configuration through support. In the mean time we will consider the Total
entry method for Roadmap.
Cheers.
Andrew
We're manually entering in "This S/C Invoice Value".
This relies on the subcontractor value being correct in terms of retention and amount previously paid - which it generally isn't. So we are completing a manual step with a calculator to obtain this value.
The better approach would be to use "Total S/C Invoices to Date". This is gross claim to date and is used by all contractors on their claims.
Hi There,
That value should be automatically calculated from the Pending Subbie
Invoices/claims linked to the Authorisation and it would be shown on the SC
claims tab.
Are you manually entering the "This Claim value" or are you configured for
Mandatory SC Pending Invoice Linking where the value is automated?
cheers
Andrew
I understand that this functionality isn't available - would be great if this could be added in.
See attached a screen shot of what we are trying to achieve - we should be able to enter the "Total S/C Invoices to Date" when starting the S/C payment.
The value claimed by subcontractors should always be reconciled back to a Total Claim to date rather than an individual invoice value.
Hi There,
Please reach out to our support and services team regarding this feature.
We can assist you to configure this methodology in your system. Consulting
involvement is recommended for the activation to ensure all your current
Subcontracts are in the correct position before activation and other
training considerations.
Cheers
Andrew
this functionality exists. paramterised