Very time consuming for QS to manually enter each variation status and change from R to A
Each variation status has a date, qty, UOM, rate ,and amount. so changing status is not as simple as just changing a letter. The variation can also be transferred.There could be an easier way by say a Right Mouse Button option.
Company | Naylor Love Construction Limited |
Job Title / Role | Management Accountant |
I need it... | 1 month |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
Hey thanks for your suggestion Tania,
We are always interested in ways to reduce clicks for our users. I guess the theory in the past has been that at the same time as changing status by click of the radio button you may also want to change values, attach documents to the content viewer, request approval, adjust Site Ref and SC ref information or skip status's eg from n to A and fill in the Subbie price at the same time.
The untransfer is also important as this will back out any auto PMW forecasting entries if this configuration option is set up. ie Transferring in the N status can be configured to write an automatic PMW forecasting entry.
Were you thinking the right click option appear on the Variation header screen? let me know how you see the right click option working. I am interested.
thanks
Andrew Tucker (Product Manager APAC)