Is there any method to restrict the CA/PM to change a PO which was already processed and committed before? (We do not want to enable PO approval system as this will reduce the efficiency)
Currently Contract admin or project manager can amend PO quantity or value easily by changing the PO qty/price. It is not controllable at all.
Can we control PO just like subbies claims that they have to raise a variation to change the subcontract sum?
Company | LORDS PROPERTY GROUP PTY LTD |
Job Title / Role | FINANCE MANAGER |
I need it... | Yesterday...Come on already |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
Hi,
Implementing PO Advanced Approvals is really the only way, thats exactly
what its for.
cheers
Andrew